You can access the weekly status reports for the public and internal stakeholders here. Our reports are written in line with our company's principles of transparency and accountability. Through these reports, you can get information about our company's overall status, project progress, financial situation, and security issues. Please remember that during funding, you can ask us any questions you may have about funds or projects. You can send your questions through our website sentinelalpha.co or via email at sentinelalpha@eolisaspace.com. You will receive a response within 24 hours at the latest.

About The Reports

Weekly Report 15.07.2024 - 21.07.2024

Updated: Aug 19

The developments discussed, decisions made during the meeting held on 21.07.2024, and the weekly progress and setbacks are outlined below:


Project Progress:


  • The rocket's nose cone design was renewed and printed. The rocket's launch date may change.

  • Rocket engines were procured.


Kickstarter and Funding:


  • Meetings were held with certain organizations to raise awareness of Eolisa Space on Kickstarter.

  • The editing of videos to be uploaded to Kickstarter has been completed, and the edited videos have been placed in the project folders.

  • The necessary verification for Kickstarter funding has been completed. Eolisa Space is now ready to initiate funding.


Intracompany Operations:


  • An observation event with a telescope was conducted (18.07.2024).

  • The EOLS telescope model was updated.

  • The "Research Center Animation" to be shared on social media was created.


Science Team:


  • The mathematics and physics sections of the book to be prepared by the science team were adjusted for the readers.

  • Some texts for topics to be published in the book have started to be prepared.


Financial Status:


  • 10 rocket engines and 10 igniters were purchased. Total amount: 2170 TL.


General Developments:


  • Posts were shared on the @eolisaspace Instagram account.

  • Feasibility reports for the Space School and Research Center were prepared.

Recent Posts

See All

Weekly Report 25.11.2024 - 01.12.2024

The weekly progress and setbacks of the company are as follows. Project Progress: The Science Team is working on the black hole project....

Weekly Report 18.11.2024 - 24.11.2024

The weekly progress and setbacks of the company are as follows. Project Progress: The work on the new magazine has been postponed to a...